What's behind the colors indicating Momentum?
What's behind the colors indicating Momentum?
Updated this week
OnsiteIQ - Symbol - Black.png

OnsiteIQ Momentum refers to the indicators layered on top of progress tracking that determine whether or not a project, specific trade, or location on a project will complete by the baseline completion date. Momentum is tracked on the Portfolio Dashboard for projects as a total, and on the Progress Tracking Table for trades and locations as totals and for each trade by location.

โ†’ Percentages & Momentum Logic

You can slice and dice the data to see progress and momentum across multiple perspectives. That includes:

  1. Portfolio progress & momentum

  2. Trade progress & momentum

  3. Location progress & momentum (by floor plan, floor level, phase, or building)

  4. Trade by location progress & momentum (by floor plan, floor level, phase, or building)

Portfolio Progress & Momentum

Portfolio Momentum Tracking - prt1

See the legends below that describe the color logic for momentum at the Portfolio level.

LOGIC 1: With Baseline Completion Dates Listed

Color/Indicator

Logic

Green/Green Triangle

Projects that are ahead of schedule or forecasted to finish within 7 days of the baseline date based on the past 30-day period production rate.

Yellow/Yellow Warning Triangle

Projects that are at risk due to lack of progress over a 30-day period or are forecasted to finish later than the baseline completion date.

Neutral

Projects without sufficient progress data to measure momentum.

Please see Set Up Your Projects for Full Schedule Tracking for information on how to enter Portfolio Baseline Completion Dates.

LOGIC 2: Without Baseline Completion Dates Listed

Color/Indicator

Logic

Yellow/Yellow Warning Triangle

Projects that have had 0% change over the past 30 days and are less than 99% complete.

Neutral

Projects that either (1) don't have sufficient progress data to measure momentum (2) have had greater than a 0% change in progress over the last 30 days.


Trade Progress & Momentum

Location Progress & Momentum

Trade by Location Progress & Momentum

See the legends below that describe the color logic for momentum at the Project level.

LOGIC 1: With Baseline Completion Dates Listed

Color/Indicator

Logic

Green

Trades and locations that are ahead of schedule or forecasted to finish within 7 days of the baseline date based on the past 2 week period production rate.

Yellow

Trades and locations that are at risk due to lack of progress over a 2 week period or are forecasted to finish later than the baseline completion date.

Neutral

Trades and locations without sufficient progress data to measure momentum.

Checkmark

Progress has reached 100%.

Please see Set Up Your Projects for Full Schedule Tracking for information on how to enter Project Baseline Completion Dates.

LOGIC 2: Without Baseline Completion Dates Listed

Color/Indicator

Logic

Green

Trade and location progress % has consistently increased over a 2 week period.

Yellow

Trade and location progress % has not made any progress over a 2 week period.

Neutral

Trade and location progress % has made some progress, but itโ€™s inconsistent.

Checkmark

Progress has reached 100%.