FEBRUARY 2025 | Momentum Reasoning
FEBRUARY 2025 | Momentum Reasoning
Updated over 2 months ago

Product Release Date: February 14, 2025

Overview

Momentum Reasoning is an enhanced feature building upon our full schedule tracking release. It provides greater clarity on construction progress against baseline schedules. This update introduces standardized language to indicate project momentum, ensuring teams can quickly assess project status at multiple levels.

What’s New?

You could already track the progress and momentum of projects in these ways:

  • Overall for a project

  • For individual trades on a project

  • For individual locations on a project (by floor plan, floor level, phase, or building)

  • For a specific trade at a specific location on a project

Now, with Momentum Reasoning, we’ve introduced clear status indicators based on momentum:

  • If baseline completion dates have been entered:

    • 🟢 Green = On-Track

    • 🟡 Yellow = Behind Schedule

  • If baseline completion dates have NOT been entered:

    • 🟢 Green = Active

    • 🟡 Yellow = Stalled

These status updates now seamlessly appear across all Portfolio Dashboard drawers and Project Progress Tracking tables for a clearer, more actionable view of progress.

Key Benefits

Quicker to Understand

Easily determine if your project is progressing fast enough to reach 100% completion before the baseline completion date—if one has been set.

Proactive Bottleneck Identification

View momentum across all levels—from the entire project to specific floors or trade locations. Identify potential delays early to address trade-specific or location-based slowdowns before they escalate.

Scalable Momentum Tracking

Track real-time milestone pacing across multiple trades and locations. Ensure consistent risk detection, allowing teams to maintain efficiency even on large-scale projects.

Enhanced Team Transparency

Centralized insights improve communication between project managers, VPs of Construction, C-Suite executives, and investors. Better transparency facilitates data-driven decision-making and keeps stakeholders aligned.


To understand how Progress and Momentum is calculated across all levels, please see What's Behind the Colors Indicating Momentum?

Please also see Set Up Your Projects for Full Schedule Tracking for information on how to enter/submit your Baseline Start and Completion Dates.


The content in this announcement represents a single point in time. Future releases may affect the information on this page.